When heavy rain occurs, water can easily rise above a small lip or edge in a valley gutter and overflow into unwanted areas. To prevent this, a properly installed drain system is essential. This blog explains how to install a drain in a valley gutter, how to prepare the area, how to secure the drain body, and how to integrate the new system with concrete work. The process also includes trenching, pipe installation, rebar dowelling, surface preparation, and final cleanup.
1. Preparing the Area for Drain Installation
A valley gutter often has a limited threshold before water spills over. To correct this, a drain must be installed at the low point. Begin by determining the exact location where water accumulates and mark that position.
Before the installation day, cut the concrete where the drain will be placed. This creates a clean opening and speeds up the workflow once concrete is scheduled for delivery.
2. Positioning and Stabilizing the Drain Body
There are different ways to secure the drain during installation. In this method:
Two small wooden stakes are driven into the ground at each side of the drain body.
A screw is installed underneath the drain to act as temporary support.
Quick-setting concrete mix (“hot mud” or red bag mix) is used to anchor the drain in place.
The fast-setting mix begins curing within minutes, so apply it sparingly to lock the drain in alignment. Once the material has firmed up, remove the wooden stakes so they do not interfere with the final concrete pour.
3. Setting the Drain Elevation
To prevent future water pooling, the concrete surface must be slightly higher than the drain grate. To achieve this:
A sheet of ¼-inch Masonite (or similar thin sheet material) is cut to fit over the drain opening.
This temporary cover protects the drain from debris and raises the surrounding concrete level slightly, ensuring water flows directly toward the drain rather than stopping before it.
4. Tying the Drain Into the Concrete Slab
To structurally lock the new concrete with the existing slab:
Drill holes into the current driveway edge.
Insert rebar dowels into the drilled holes.
Tie the rebar together around the drain zone.
This reinforcement prevents future separation or cracking between the old and new concrete sections.
5. Pouring the Concrete
In this application, two yards of concrete were ordered with a 2% chemical accelerator. The accelerator helps the concrete set faster, especially when rain is in the forecast.
Key concrete placement notes:
The mix was poured on the dry side to maintain workability and minimize washout risk.
A concrete vibrator was used to work the material under and around the drain body.
During pouring, some water flowed toward the work area. Excess water was swept away and the concrete surface was reworked until the desired finish was achieved.
Despite moisture interruptions, maintaining the surface and working the cream outward allows for proper finishing.
6. Finishing and Surface Work
Once the concrete is distributed:
Continue floating and troweling until the surface is uniform.
Ensure the finishing slope directs water toward the drain opening.
Maintain a consistent slope and avoid creating any depressions near the drain that could cause puddling.
After finishing, allow the slab to cure undisturbed.
7. Installing the Remaining Drain Line
The following day, the remaining sections of drainage pipe can be installed. If the main trenching was completed earlier, this step involves:
Inserting the final pipe section.
Ensuring bell ends face the proper direction for flow.
Maintaining proper slope throughout the run.
Keeping pipe joints clear of soil to prevent blockages.
Each connection must seat fully into the bell end to maintain water-tightness.
8. Final Backfilling and Surface Restoration
Once the piping is complete:
Backfill the trench using soil in layers.
Compact each layer to prevent future settling.
Replace surface materials such as grass, sod, gravel, or topsoil.
Trim any excess membrane or landscape fabric so it lies flat.
Smooth the area using a rake or broom.
This ensures the completed installation appears clean and blends with the surrounding landscape.
9. Importance of Proper Transition Around the Drain
If the concrete around the drain is even slightly low, water may pool before entering the slot. Raising the concrete by a quarter inch around the drain eliminates this issue, allowing water to flow freely without hesitation. This small adjustment is essential for long-term drainage performance.
10. Maintenance After Installation
After the system is installed:
Remove any remaining construction debris.
Clear dirt from the drain opening.
Inspect each pipe section to ensure soil did not shift during backfill.
Confirm proper water flow during a controlled test or the next rainfall.
Routine checks ensure the drain continues to function without blockage.
Conclusion
This installation process transforms a problematic valley gutter into a controlled and efficient drainage path. By cutting the concrete, anchoring the drain body, establishing proper elevation, reinforcing the area with rebar, pouring concrete with correct slope, and installing drainage piping with consistent fall, the system prevents overflow and directs water safely away from vulnerable areas.
This method ensures durable long-term performance, reduced risk of water damage, and improved surface drainage during heavy weather conditions